Chapter 10 Project Quality Management

Unit Test 10

1、单选题:
‏( )occurring prior to delivery / shipment of the product or service, to the customer.‎‏‎
选项:
A: Internal failure costs
B: Prevention Costs
C: Appraisal Costs
D: External Failure Costs
答案: 【 Internal failure costs

2、单选题:
‍(   ) conform with the cost of conformance.​‍​
选项:
A: Internal failure costs and Prevention Costs
B: Internal failure costs and External Failure Costs
C: Appraisal Costs and Prevention Costs
D: Prevention Costs and External Failure Costs
答案: 【 Appraisal Costs and Prevention Costs

3、单选题:
​The most common quality management tool exclude (  )​
选项:
A: The flow chart
B: Affinity diagrams
C: Cause-and-Effect Diagram
D: Mind mapping.
答案: 【 Mind mapping.

4、多选题:
‏(    )  are the most common quality improvement tools. ‌
选项:
A: Affinity diagrams
B: Plan-do-check-act
C: Six Sigma
D: Cause-and-Effect Diagram
答案: 【 Plan-do-check-act;
Six Sigma

5、判断题:
‎Plan-do-check-act cycle is the basis for quality improvement.‌
选项:
A: 正确
B: 错误
答案: 【 正确

6、判断题:
​The cost of preventing mistakes is generally much higher than the cost of correcting them when are found by inspection.‏
选项:
A: 正确
B: 错误
答案: 【 错误

Chapter 11 Project Communication Management

Unit Test 11

1、单选题:
‎(  )used for large complex information sets, or for large audiences.‌
选项:
A: Interactive communication
B: Pull communication
C: Interpersonal communication
D: Push communication.
答案: 【 Pull communication

2、单选题:
‌(   ) perform a multidirectional exchange of information between two or more parties.‎‌‎
选项:
A: Interactive communication
B: Push communication
C: Pull communication
D: Public communication.
答案: 【 Interactive communication

3、单选题:
‍Which of the following statements about Manage Communications is false?( )‏‍‏
选项:
A: Manage Communications is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information.
B: This process enables an efficient information flow between the project team.
C: This process does not need to be performed throughout the process.
D: The Manage Communications process identifies all aspects of effective communication.
答案: 【 This process does not need to be performed throughout the process.

4、多选题:
‎The mechanisms by which information is exchanged can be in:( )‏‎‏
选项:
A: Written form 
B: Spoken form
C: Through gestures
D: Choice of words.
答案: 【 Written form ;
Spoken form;
Through gestures;
Choice of words.

5、多选题:
‍Factors that can affect the choice of communication technology include( )​‍​
选项:
A: Urgency of the need for information
B: Availability and reliability of technology
C: Ease of use
D: Project environment
答案: 【 Urgency of the need for information;
Availability and reliability of technology;
Ease of use;
Project environment

6、判断题:
‏Communication models can represent the communication process in its most basic linear. ‎
选项:
A: 正确
B: 错误
答案: 【 正确

7、判断题:
‍Work performance data contains data on the types and quantities of communications that have actually been distributed. ​
选项:
A: 正确
B: 错误
答案: 【 正确

Chapter 12 Project Stakeholder Management

Unit Test 12

1、单选题:
‍Which of the following statements about Identify Stakeholders is false?( )‌‍‌
选项:
A: It is repeated as necessary
B: It should be performed at the start of each phase
C: Each time the identification process is repeated, the project management plan components should be consulted
D: This process does not need to be performed periodically 
答案: 【 This process does not need to be performed periodically 

2、单选题:
​The engagement level of stakeholders can be divided into(  ) categories.‏
选项:
A: Four
B: Five
C: Six
D: Seven 
答案: 【 Five

3、单选题:
‍(  ) is the process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.‍
选项:
A: Manage Stakeholder Engagement
B: Plan Stakeholders Engagement    
C: Monitor Stakeholder Engagement    
D: Identify Stakeholders  
答案: 【 Manage Stakeholder Engagement

4、单选题:
‍A stakeholder engagement assessment matrix supports comparison between the current engagement levels of stakeholders and (   ) required for successful project delivery.​‍​
选项:
A: The standard engagement levels
B: The desired engagement levels
C: The maximum engagement levels
D: The minimum engagement levels
答案: 【 The desired engagement levels

5、多选题:
‌Which level of Stakeholder Engagement are aware of the project and potential impacts?( )‏
选项:
A: Resistant
B: Neutral
C: Supportive
D: Leading
答案: 【 Neutral;
Leading

6、判断题:
​The stakeholder engagement assessment matrix monitors stakeholder engagement through tracking changes in level of engagement for each stakeholder. ‎
选项:
A: 正确
B: 错误
答案: 【 正确

7、判断题:
​It is likely that any project documents will be an input for the initial stakeholder identification. ‏
选项:
A: 正确
B: 错误
答案: 【 错误

Chapter 13 Project Resource Management

Unit Test 13

1、单选题:
‎Hierarchical charts exclude (  )‌‎‌
选项:
A: Work breakdown structures
B: Resource breakdown structure
C: Assignment Matrix
D: Organizational breakdown structure
答案: 【 Assignment Matrix

2、单选题:
‌The tools of estimate activity resources exclude ( )‌‌‌‌‌
选项:
A: Analogous estimating
B: Parametric estimating
C: Bottom-up estimating 
D: Interval estimating
答案: 【 Interval estimating

3、多选题:
‌Resource categories in the resource breakdown structure include (  )‎‌‎
选项:
A: Labor
B: Material
C: Equipment
D: Supplies
答案: 【 Labor;
Material;
Equipment;
Supplies

4、多选题:
‍How do we measure performance? (  )‏
选项:
A: Observation
B: Information collection
C: Comparison between planned deliverables and current situation
D: Reporting
答案: 【 Observation;
Information collection;
Comparison between planned deliverables and current situation;
Reporting

5、多选题:
‌The key benefit of the Estimate Activity Resources is that it identifies the (   ) of resources required to complete the project.‏‌‏
选项:
A: Type
B: Quantity
C: Quality 
D: Characteristics
答案: 【 Type;
Quantity;
Characteristics

6、判断题:
‏Planning for physical and human resources is much less predictable in projects with high variability. ‍
选项:
A: 正确
B: 错误
答案: 【 正确

7、判断题:
‌Project resources can only be obtained from outside the organization through a procurement process.&nb

剩余75%内容付费后可查看