1、单选题:
Which of the following items belongs to the engineering project?
选项:
A: A manned spacecraft launch
B: " Five one "project
C: Develop a piece of software
D: Construction of the Beijing-Shanghai express railway
答案: 【 Construction of the Beijing-Shanghai express railway】
2、单选题:
The temporary nature of projects indicates that a project
选项:
A: has a short duration
B: has a definite beginning and end
C: has not adequately considered
D: can achieve their goals in a short period of time
答案: 【 has a definite beginning and end】
3、单选题:
An electric utility authorizes a project to build a substation to serve a new industrial park,which is the factor that led to the creation of the project?
选项:
A: Economic changes
B: Customer request
C: Stakeholder demands
D: Legal requirement
答案: 【 Customer request】
4、多选题:
Examples of tangible elements include:
选项:
A: Monetary assets
B: Stockholder equity
C: Public benefit
D: Utility
答案: 【 Monetary assets;
Stockholder equity;
Utility】
5、判断题:
Projects are temporary, so their deliverables can not exist beyond the end of the project.
选项:
A: 正确
B: 错误
答案: 【 错误】
6、判断题:
Deliverables may be tangible or intangible.
选项:
A: 正确
B: 错误
答案: 【 正确】
7、判断题:
PMI defines business value as the net quantifiable benefit derived from a business endeavor. The benefit is tangible.
选项:
A: 正确
B: 错误
答案: 【 错误】
Chapter3 ProjectManagementBodyofKnowledge
UnitTest3
1、单选题:
( )is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.
选项:
A: Direct and Manage Project Work
B: Develop Project Management Plan
C: Monitor and Control Project Work
D: Perform Integrated Change Control
答案: 【 Develop Project Management Plan】
2、单选题:
A project may be managed in ( ) separate scenarios:
选项:
A: Two
B: Three
C: Four
D: Five
答案: 【 Three】
3、单选题:
Which of the following statements is false?
选项:
A: Project management focuses on interdependencies within a project.
B: Program management focuses on the interdependencies between projects.
C: Programs have defined objectives.
D: Programs are managed by program managers.
答案: 【 Programs have defined objectives.】
4、单选题:
Which of the following has a priority?
选项:
A: Portfolios
B: Projects
C: Programs
D: Subsidiary portfolios
答案: 【 Portfolios】
5、多选题:
PMBOK Key Components in Projects include:
选项:
A: Project life cycle
B: Project management processes
C: Project Management Process Group
D: Project Management Knowledge Area
答案: 【 Project life cycle;
Project management processes;
Project Management Process Group;
Project Management Knowledge Area】
6、多选题:
The following options belong to PMBOK Knowledge Areas are
选项:
A: Project Integration Management
B: Project Cost Management
C: Project Resource Management
D: Project Procurement Management
答案: 【 Project Integration Management;
Project Cost Management;
Project Resource Management;
Project Procurement Management】
7、多选题:
Data analysis techniques that can be used for this process include:
选项:
A: Data audit
B: Alternatives analysis.
C: Document analysis.
D: Root cause analysis (RCA).
答案: 【 Alternatives analysis.;
Document analysis.;
Root cause analysis (RCA).】
8、判断题:
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
选项:
A: 正确
B: 错误
答案: 【 正确】
9、判断题:
Partial change completion may not cause inconsistencies and later delays due to incomplete steps or corrections.
选项:
A: 正确
B: 错误
答案: 【 错误】
Chapter4 ProjectSuccess
UnitTest4
1、单选题:
Project success factors exclude
选项:
A: Communication skills
B: Obtaining commitment of project team
C: Bureaucracy
D: Recognising the importance of people
答案: 【 Bureaucracy】
2、单选题:
Product life cycles may be produced by a
选项:
A: Portfolios
B: Project
C: Program
D: Subsidiary portfolio
答案: 【 Project】
3、单选题:
Within a project life cycle, there are generally one or more phases that are associated with the development of the product, service, or result. These are called
选项:
A: a predictive life cycle
B: an incremental life cycle.
C: a development life cycle.
D: an iterative life cycle
答案: 【 a development life cycle.】
4、多选题:
Which of the following is true?
选项:
A: Systems can be optimized.
B: Systems are linear in responsiveness.
C: Systems and their components can be optimized at the same time.
D: System components can be optimized.
答案: 【 Systems can be optimized.;
System components can be optimized.】
5、多选题:
Sources of Project Failure include:
选项:
A: Failure to establish a governance structure appropriate to the needs of the project
B: Lack of clearly defined scope for team members
C: Adequately defined tasks
D: No definition of project’s goals
答案: 【 Failure to establish a governance structure appropriate to the needs of the project;
Lack of clearly defined scope for team members;
No definition of project’s goals】
6、判断题:
The programs or projects of the portfolio must necessarily be interdependent or directly related.
选项:
A: 正确
B: 错误
答案: 【 错误】
7、判断题:
The project charter is defined as a document issued by the project manager.
选项:
A: 正确
B: 错误
答案: 【 错误】
8、判断题:
Enterprise environmental factors (EEFs) refer to conditions, under the control of the project team, that influence, c